Interconnected electricity networks -- the cornerstone of the European system and designed to improve security of supply -- made it possible to contain the massive power outage on the Iberian peninsula.

Change text size:

"The grids are interconnected, which is common as it helps to manage the export and import of electricity, hence, improving the reliability of supply," said Onyema Nduka, senior lecturer in power sustainability at Royal Holloway University of London.

But he added: "While electricity outages are rare in European countries they are possible, as the events in Portugal and Spain have shown.

"Ideally, redundancies are built into the system such as having multiple supply points, backup generators sited at different locations, interconnected wires, cables, etc."

Grazia Todeschini, reader in engineering at King's College London, said Europe has "the largest synchronous electrical grids in the world", supplying over 400 million customers in 32 countries and most of the EU.

"This allows power exchange between countries but under very special and extreme situations it may mean that outages may propagate across different countries," she added.

That happened on Monday, when the outage in Spain also hit its neighbour Portugal.

The Iberian peninsula, situated at the edge of the European electricity network, is by its location an "electricity peninsula".

Spain and France, which are separated by the Pyrenees, have had an interconnection capacity of 2.8GW since 2015, with plans to increase that to 5 GW by 2028. Spain is also interconnected with Morocco via a 700MW line.

The stability of electricity networks "is related to a very close balance between electricity generation and demand", said Todeschini.

"Some measures exist to limit the impact of outages to small areas but when the power unbalance is too large, these outages may spread very quickly and very far."

- Extremely rare event -

According to French high-voltage network operator RTE, Spain saw a loss of 15GW of production in a matter of seconds, leading to a nationwide outage.

RTE immediately mobilised to help Spain via interconnectors between the two countries, allowing it to gradually input up to 2GW into the Spanish network depending on local demand.

To tackle such situations, RTE explained that protocols have been put in place, with several manual and automatic "defence barriers" implemented to handle all possible situations, from limiting the spread of an incident to restoring power to consumers in the event of a black-out.

On Monday, RTE activated automatic security measures which cut the interconnectors, isolating the Iberian peninsula and stopping the instability from spreading to central Europe, said Rystad Energy, which specialises in energy research.

"France's role in the crisis was critical," it added. "The sudden drop in Iberian demand forced the country to temporarily reduce generation output and re-route its energy flows," it added.

Notably, that included a shut-down of the Golfech nuclear power plant in southwest France at about the same time as the outage in Spain and Portugal.

"Once stability was partially restored to Spain, France resumed limited exports to assist with recovery," Rystad added.

On Monday, the Iberian network was automatically disconnected from the European network from 1038 to 1130 GMT, when the electricity line between France and Spain was restarted, RTE said.

The network then took several hours to be completely restored, area by area, in Spain and Portugal.

"What's certain is that cooperation and interconnections between France and Germany and between RTE... enabled and facilitated, through cooperation, the faster recovery of electricity consumption in Spain," said French energy minister Marc Ferracci on RTL radio.

D.Vanacore--PV

Featured

Michigan Pizza Driver Halts $785K GoFundme After Viral Prank

Walt Zerod, a Michigan father of four who became the center of a viral online controversy, has paused a crowdfunding campaign that raised nearly $785,000. The Red Baron delivery driver announced on Thursday that he is closing the page to focus on his family during the holiday season.

Kate McClymont Testifies at Alan Jones Trial Over Reporting Methods

Investigative journalist Kate McClymont took the stand in the thirteenth week of the trial against former radio personality Alan Jones, facing rigorous cross-examination over her reporting methodology. Her testimony focused on text message exchanges with police and the verification process that led to the legal proceedings.

Chervon Names Doug Palmer Vice President of Finance - Canada

TORONTO, ON / ACCESS Newswire / November 5, 2026 / Effective November 9, 2026, Chervon names Doug Palmer Vice President of Finance - Canada, reporting to Neil Harrison, Vice President and Managing Director of Chervon Canada. He will also have a dotted-line reporting relationship to Ryan Wang, Chief Financial Officer, Chervon NA.

Polaris Renewable Energy Announces Q3 2026 Results

TORONTO, ON / ACCESS Newswire / November 5, 2026 / Polaris Renewable Energy Inc. (TSX:PIF) ("Polaris Renewable Energy" or the "Company"), is pleased to report its financial and operating results for the three and nine months ended September 30, 2026. This earnings release should be read in conjunction with the Company's consolidated financial statements and management's discussion and analysis, which are available on the Company's website at www.PolarisREI.com and have been posted on SEDAR+ at www.sedarplus.ca. The dollar figures below are denominated in US Dollars unless noted otherwise.

Change text size: